At Dominion Energy, we are dedicated to maintaining reliable and secure electric service in the communities we serve. The Yadkin-Fentress 500 kilovolt (kV) Electric Transmission Line Project rebuilds approximately 13.5 miles of existing 500 kV transmission line that runs from the Yadkin Substation on Yadkin Road to the Fentress Substation on Meredith Drive and Fentress Loop in Chesapeake, Virginia.
This project is needed to replace aging equipment and to add additional infrastructure to deliver the renewable energy generated by the Coastal Virginia Offshore Wind (CVOW) project. This transmission line was built on lattice structures. We are wrecking the existing, aging 500 kV line and building two 500 kV transmission lines on separate monopole structures. The approach is to maximize the use of the existing transmission corridor by changing the current lattice-type structure so two independent transmission lines can be built without requiring new or expanded right of way.
We hosted a community meeting in April 2024 to share more information about this project and for you to speak with project team members. On June 13, 2024, Dominion Energy filed its application with the SCC. In February 2025, we held two community meetings to prepare for pending construction. On February 28, 2025, the SCC issued its Final Order approving the project. You can learn more by clicking the blue Legal button at the top of this page.
A construction schedule is below. More details will be provided as activities progress.
Construction Schedule
(Schedule is subject to change pending final approvals, permits, weather, and progress. Upon completion, we will restore the right of way.)
Phase 1: Yadkin Substation – Weiss Lane
March 2025: Construction begins
June 2025: Finish rebuilding Line 588
September 2025: Finish building Line 5005
Phase 2: Appaloosa Trail – Holmes Trail
April 2025: Construction begins
March 2026: Finish rebuilding Line 588
and finish building Line 5005
Phase 3: Holmes Trail – Fentress Substation
June 2025: Construction begins
June 2026: Finish rebuilding Line 588
December 2026: Finish building Line 5005
Yadkin-Fentress Construction Phases Map
There may be some traffic delays.
Noise levels may be high at times; permits are in place.
Access to surrounding neighborhoods will not be impacted.
There are no planned service interruptions for this project
Most work will be completed between 7 a.m. and dusk, typically on Monday - Saturday. Sunday work may be permitted in some cases.