June
Projected in-service date
Summer
Construction complete, restoration of work area begins.
Q1
Requested date for SCC approval
December 21st
The SCC issued its final order approving the Chesterfield-Lakeside transmission project
November 13th
The SCC Hearing Examiner's Report was issued in response to the proposed project
November 5th
Public Evidentiary Hearing, 10:00 a.m., SCC, Richmond
October 5th
Dominion Energy Rebuttal due
August 24th
Staff Report Due
August 24th
Public Comments
August 3rd
Notices of Participation
Q3 - Q4 2018
Procedural order issued; public hearing scheduled
July 12th
Landowner, Gov't Official and Public Notice
June 12th
The SCC issued an Order of Notice and Hearing, outlining the procedural schedule for the case
Late May 2018
File application with the SCC
May 16-17
Host two public open houses
April
Meet with local elected officials; Project website launched