Late 2025
Existing overhead transmission line and transition station removal (second detour of Four Mile Run Trail); Target completion date. Restoration of work area.
Mid - Late 2024
Replace existing chain-link fence with new metal mesh security fence
2023 - 2024
Substation construction. Underground transmission line construction.
February 2023
Anticipated completion of the boardwalk for the Four-Mile Run diversion around the Glebe Substation
December 2022
Launch pit sound wall installation completed
August
Begin installing launch pit in Potomac Yard Shopping Center.
Summer 2022
Select contractors
June - September 2022
Four Mile Run Trail closed around Glebe Substation while we install Temporary Boardwalk Diversion.
Late May 2022
Arlington County and VDOT approve Four Mile Run detour plans.
May 11th
Pre-Construction Virtual Community Meeting
September 27th
The SCC issued its final order approving the Glebe Rebuild Project
Document
Document
August 13th
The SCC Hearing Examiner’s Report was issued in response to the project
Document
Document
July 16th
Any interested person may file written or electronic comments on the application (referencing Case No. PUR-2019-00040).
July 9th
Dominion Energy may file any rebuttal
March 25th
The SCC issued an Order of Notice and Hearing
Document
Document
March 7th
Submit application to Virginia State Corporation Commission (SCC)
View Legal
View Legal
February
Ongoing meetings with community/civic associations
Late January 2019
Submitted 2202 letters to localities; Provided update to locality staff; Sent cultural advocacy letters to stakeholders
June 25th
The SCC staff must file a report and exhibits on its investigation of Dominion Energy’s application.